Part R - Update to Building Regulations

Part R - Update to Building Regulations

Physical High-Speed Infrastructure for New Dwellings

Two new Approved Documents have been published by the Department for Levelling Up, Housing and Communities. These are as follows:

  • Approved Document R Volume 1: Physical infrastructure and network connection for new dwellings

  • Approved Document R Volume 2: Physical infrastructure for high-speed electronic communications networks.

  • It is necessary to have the following installed in newly constructed dwellings as part of the new Part R requirements:

  • Install a gigabit-ready physical infrastructure necessary for gigabit-capable connections. For example, ductwork, chambers, cabling and network termination points at each dwelling.

  • If this is not possible then the developer is expected to provide the infrastructure as close as is reasonably practicable

  • Install a functioning gigabit-capable connection. For example, fibre optic cable or other technological means of facilitating such a connection. This is capped at £2,000 per dwelling.

  • If the developer is unable to secure a gigabit-capable connection within the cost cap, the next fastest technology connection can be installed.

Approved Document R Volume 2 provides guidance on how to build in accordance with the high-speed ready provisions found in R1 in Schedule 1 to the Building Regulations when new buildings are erected or when existing buildings are subject to major renovation works.

Transitional arrangements

The New Approved Documents come into force on 26th December 2022

The changes will not apply if an Initial Notice is submitted before this date, provided the work is started on-site within 12 months.

When you apply for multiple buildings at a site, the first occasion of building work can serve as a transitional provision that applies to all of them.

Previous
Previous

H&S CDM Regulations

Next
Next

Class B - Permitted Development Temporary use of land